As part of the site survey our contractors Landscope will be carrying out, they will be capturing mobile data on all the roads and car parks across campus from Monday 15 - Friday 19 April.
Until Friday 14 June, they'll also be undertaking the underground, topographic and tree surveys. You may see survey staff in high visibility vests with equipment in many areas of campus, however the work will all be carried out outside and will not generate any noise. The programme of work is as follows;
Zone
|
Underground and
topographic survey
|
Tree survey
|
B
|
10-14 Jun
|
|
D
|
29 Apr to 3 May
|
TBC
|
E
|
27 to 31 May
|
F
|
15-26 Apr
|
|
G
|
6-10 May
|
8-12 Apr
|
H
|
20-24 May
|
15-19 Apr
|
I
|
3 to 7 June
|
22-26 Apr
|
J
|
6-17 May
|
|